![Construction and detailed design of gas pipeline in Poland](https://cdnpreprodanteagroup.blob.core.windows.net/prod/media/resized/10/74a48167-f3ae-4ad6-b469-d902d15d57d6/autox580_gas-pipeline-pogorska-wola-tworzen-1.jpg)
Construction and detailed design of gas pipeline in Poland
- International
- Projects
- Construction and detailed design of gas pipeline in Poland
Pogorska Wola - Tworzen high pressure gas pipeline
Preparation of the construction and detailed design together with the author's supervision for the investment task "Pogorska Wola - Tworzen Gas Pipeline", carried out as part of the construction of the Hermanowice - Strachocina - Pogorska Wola - Tworzen - Tworog - Odolanow gas pipeline.
The DN1000 8.4 MPa Pogorska Wola-Tworzen gas pipeline project with a length of approx. 168 km is an important element of the North-South Gas Corridor. The gas pipeline route will pass through three voivodships - Malopolskie, Swietokrzyskie and Slaskie and was divided into three sections:
- Pogorska Wola-Palecznica, about 78 km long
- Palecznica-Braciejowka, about 56 km long
- Braciejowka-Tworzen, about 34 km long
The gas pipeline is under construction now and it's planned to be completed in 2021.