Construction of the Dabrowice Wind Farm in Poland

Construction of the Dabrowice Wind Farm in Poland

Owner’s Engineer and Supervisor for the construction of the Dabrowice Wind Farm in Poland.

The wind farm is located in Dabrowice - a town in  the northern part of Lodzkie Province. The wind farm consists of 13 turbines GE 2.75-120. The project also includes access roads, assembly yards, 30kV cable network, a control network, a teletechnical network, and an intermediate 30 kV connection cabinet as well as a GPZ substation. The task was commissioned by  Engie Zielona Energia Sp. z o.o., an Engie Group company.

 

The scope of work

  • Preparation of the project implementation plan, including schedule, organization, budget
  • Preparation of complete tender documentation, support during the preparation and running of tenders for the selection of suppliers and works contractors
  • Design and implementation stage, including fulfilling site manager duties, supervision and coordination of works, carrying out acceptance, carrying out author's supervision within all required industries
  • Guarantee stage including site inspections

This website uses cookies

Functional and analytical cookies are placed with every visit without requiring permission. Use of the Social Media buttons depends on the privacy statement and cookie policy of the relevant social network. Targeting cookies from third parties are only placed if you give your consent. Select the type of cookies you want to accept.